defirisk.co
rubric v1.7.0

Audit-to-deploy gap

Centrifuge's assessment for RD-F-006 — scored green on the v1.7.0 rubric. The evidence below is the curator's reasoning for this score.

Evidence summary #

V3.1 (January 2026): multiple audits concluded Nov-Dec 2025 before Jan 20 2026 deploy. Gap between last pre-deploy audit (Dec 2025) and deploy (Jan 20 2026) is approximately 20-50 days — within the ≤60-day green threshold. Sherlock deployment verification conducted Feb 2026 post-deploy.

Sources #

Methodology #

Measure the number of days between the audit report sign-off date and the mainnet deploy of the audited bytecode.

See the full factor methodology and distribution across all protocols →

rubric_version v1.7.0 protocol centrifuge factor RD-F-006 score green collected_at 2026-04-30 21:19:10