Audit-to-deploy gap
Centrifuge's assessment for RD-F-006 — scored green on the v1.7.0 rubric. The evidence below is the curator's reasoning for this score.
Evidence summary #
V3.1 (January 2026): multiple audits concluded Nov-Dec 2025 before Jan 20 2026 deploy. Gap between last pre-deploy audit (Dec 2025) and deploy (Jan 20 2026) is approximately 20-50 days — within the ≤60-day green threshold. Sherlock deployment verification conducted Feb 2026 post-deploy.
Sources #
- Audit
- https://etherscan.io/address/0x0C1fDfd6a1331a875EA013F3897fc8a76ada5DfCretrieved 2026-04-27
Methodology #
Measure the number of days between the audit report sign-off date and the mainnet deploy of the audited bytecode.